@MastersThesis{Santos:2018:PrMéEs,
               author = "Santos, Lucas Pereira dos",
                title = "Proposta de um m{\'e}todo de estimativa de esfor{\c{c}}o para 
                         projetos de desenvolvimento de software cr{\'{\i}}ticos",
               school = "Instituto Nacional de Pesquisas Espaciais (INPE)",
                 year = "2018",
              address = "S{\~a}o Jos{\'e} dos Campos",
                month = "2018-12-05",
             keywords = "Desenvolvimento de software, estimativa de esfor{\c{c}}o, 
                         software cr{\'{\i}}tico para seguran{\c{c}}a, software 
                         embarcado, COCOMO, DO-178C, software development, effort 
                         estimation, safety-critical software, embedded software.",
             abstract = "Encontrar a causa raiz para as diversas falhas e atrasos em 
                         projetos de desenvolvimento de software tem sido objeto de estudo 
                         de diversos pesquisadores nos {\'u}ltimos anos. Estimar 
                         corretamente os custos e prazos do projeto antes de inici{\'a}-lo 
                         {\'e} uma etapa importante do processo de desenvolvimento que 
                         n{\~a}o deve ser ignorada. Essa disserta{\c{c}}{\~a}o apresenta 
                         um modelo de estimativa de esfor{\c{c}}o para projetos de 
                         desenvolvimento de software cr{\'{\i}}ticos, baseado na 
                         adapta{\c{c}}{\~a}o do modelo COCOMO II de modo a considerar os 
                         aspectos de seguran{\c{c}}a definidos pela norma RTCA DO-178C. O 
                         desenvolvimento deste modelo inclui o estudo da literatura e dos 
                         conceitos de estimativa de esfor{\c{c}}o em projetos de 
                         desenvolvimento de software em geral, em especial o COCOMO II; a 
                         apresenta{\c{c}}{\~a}o da norma DO-178C, seus processos, 
                         caracter{\'{\i}}sticas e aplica{\c{c}}{\~a}o; o estudo de caso 
                         da aplica{\c{c}}{\~a}o do COCOMO II em um projeto real executado 
                         pela ind{\'u}stria aeron{\'a}utica brasileira seguindo e 
                         cumprindo com todos os objetivos da DO-178C, analisando o 
                         esfor{\c{c}}o real demandado por tal projeto em cada uma de suas 
                         fases; a aplica{\c{c}}{\~a}o do modelo proposto neste mesmo 
                         projeto, comparando os resultados com rela{\c{c}}{\~a}o aos 
                         obtidos pela estimativa realizada com o COCOMO II; a 
                         aplica{\c{c}}{\~a}o do modelo proposto no projeto de miss{\~a}o 
                         espacial denominado FireSat. Com rela{\c{c}}{\~a}o a 
                         compara{\c{c}}{\~a}o com o COCOMO II, a aplica{\c{c}}{\~a}o do 
                         modelo proposto apresentou uma melhor precis{\~a}o na estimativa 
                         de esfor{\c{c}}o, com um erro relativo de 10,33% contra 31,3% 
                         obtidos pelo COCOMO II. Uma melhor performance do modelo proposto 
                         tamb{\'e}m foi observada na estimativa do prazo para 
                         desenvolvimento do projeto. No entanto, na estimativa do tamanho 
                         m{\'e}dio da equipe o modelo COCOMO II se mostrou mais aderente 
                         que o modelo proposto por esta disserta{\c{c}}{\~a}o. Na 
                         compara{\c{c}}{\~a}o com a estimativa realizada para o projeto 
                         FireSat, o modelo proposto apresentou resultados coerentes com o 
                         estimado originalmente. Deste modo, conclui-se que o modelo 
                         proposto {\'e} mais indicado para estimativa de esfor{\c{c}}o em 
                         projetos de desenvolvimento de software cr{\'{\i}}tico que 
                         seguem os processos estabelecidos pela DO-178C, com espa{\c{c}}o 
                         para se tornar ainda mais preciso mediante realiza{\c{c}}{\~a}o 
                         dos trabalhos futuros recomendados. ABSTRACT: Finding the root 
                         cause for the various failures and delays in software development 
                         projects has been the subject of study by several researchers in 
                         recent years. Properly estimating project costs and deadlines 
                         before starting it is an important step in the development process 
                         that should not be ignored. This work presents an effort 
                         estimation model for safety-critical software development 
                         projects, based on the adaptation of the COCOMO II model in order 
                         to consider the safety aspects defined by the standard RTCA 
                         DO-178C. The development of this model includes the literature 
                         review and the study of the software effort estimation concepts, 
                         focused mainly on the COCOMO II model; the introduction of the 
                         DO-178C standard, its processes, characteristics and application; 
                         the case study of an application of COCOMO II in a real project 
                         executed by the Brazilian aeronautical industry, which has 
                         followed and met all the objectives of the DO-178C, analyzing the 
                         real effort demanded by such project and comparing it to the 
                         COCOMO II estimated values; the application of the proposed model 
                         in this same project, comparing the results with those obtained by 
                         the estimation with COCOMO II and the application of the proposed 
                         model in the space mission project called FireSat. Compared with 
                         COCOMO II, the application of the proposed model presented a 
                         better accuracy in the effort estimation, with a relative error of 
                         10.33% versus 31.3% obtained by COCOMO II. A better performance of 
                         the proposed model was also observed in the schedule estimation of 
                         the project. However, in the team size estimation, the COCOMO II 
                         model proved to be more adherent than the model proposed by this 
                         work. In comparison with the estimation made for the FireSat 
                         project, the proposed model presented results consistent with the 
                         original estimation. Thus, it is concluded that the proposed model 
                         is more suitable for safety-critical software effort estimation 
                         development projects that follow the processes established by the 
                         DO-178C, with room to become even more precise if further research 
                         is carried out following the recommendations presented in this 
                         work.",
            committee = "Sant'Anna, Nilson (presidente) and Ferreira, Maur{\'{\i}}cio 
                         Gon{\c{c}}alves Vieira (orientador) and Ribeiro, Edson Alves and 
                         Silva, Rodrigo Rocha",
         englishtitle = "An effort estimation model for safety-critical software 
                         development projects",
             language = "pt",
                pages = "183",
                  ibi = "8JMKD3MGP3W34R/3S5RGU5",
                  url = "http://urlib.net/ibi/8JMKD3MGP3W34R/3S5RGU5",
           targetfile = "publicacao.pdf",
        urlaccessdate = "25 abr. 2024"
}